Public Storage - Atlanta, GA
Site-work, including crushing of old building pad, to make way for a new self- storage building.
Roof Drainage System Installation: We installed 700 LF of 8-inch HDPE piping to ensure efficient roof drainage, protecting the structure and surrounding area from water accumulation.
Storm Drainage Installation: Our team installed 814 LF of storm drain pipe to manage runoff and prevent flooding, ensuring proper water flow throughout the site.
Water Quality Unit Installation: We installed one Barracuda water quality unit to enhance stormwater treatment, effectively removing contaminants and ensuring compliance with environmental regulations.
Underground Detention System Installation: We installed an ADS MC7200 underground detention system, consisting of 34 chambers, to manage and control stormwater runoff, reducing the risk of flooding and maintaining site sustainability.
Sanitary Sewer Installation: We laid 586 LF of sanitary sewer pipe to provide a reliable and efficient wastewater management system for the project.
Grease Trap Installation: We installed one 1,000-gallon grease trap to manage waste from food-related operations, ensuring proper treatment and compliance with environmental and health regulations.
Pump Station Installation: Our team installed one 48" x 144" duplex fiberglass pump station, complete with two Barns pumps, to provide reliable pumping capabilities for wastewater and stormwater management.