Overlook (Madison Apts.) - Canton, GA
19 acres of heavy clearing, grading, and underground utility installation for multi-family residence development
Heavy Clearing: We performed heavy clearing across 19 acres of land to prepare the site for further construction, removing vegetation, debris, and any obstructions to provide a clean, level foundation for development.
Dirt Moving: Our team moved 137,060 CY of dirt to grade the site and establish the proper foundation and elevation for subsequent infrastructure installations.
Storm Pipe Installation: We installed 4,729 LF of storm pipe, ensuring effective stormwater management and drainage to prevent flooding and maintain site sustainability.
Roof Drainage Pipe Installation: To manage water runoff, we installed 3,000 LF of roof drainage pipe, directing water away from buildings and foundations to avoid water damage and structural issues.
Sanitary Sewer Pipe Installation: We laid 3,830 LF of sanitary sewage pipe to establish a reliable and efficient wastewater management system, ensuring proper sanitation and drainage across the site.
Domestic Water Pipe Installation: Our team installed 820 LF of domestic water pipe, ensuring a consistent and reliable water supply to the site’s infrastructure.
Fire Water Pipe Installation: We installed 3,880 LF of fire water pipe, providing the necessary infrastructure to support a comprehensive fire suppression system, enhancing safety across the site.
Modular Block Retaining Wall Installation: We installed 31,034 LF of modular block retaining walls, providing structural support and preventing erosion while enhancing the site’s aesthetic and functional design.